Peace with God through Jesus Christ

Building Project Update – Oct. 8, 2018

Completed Projects

  • Removal of asphalt in East parking lot
  • Removal of canopy over McConnell Street entrance

Current Projects In Process

  • Site preparation work underway on east side of facility
  • Working on footings for new construction where the canopy was

Weeks of October 8 and 15

  • Excavation work, backfilling, and foundation work will continue along the east side of the existing building in preparation for the new construction
  • Xcel Energy will remove the center power pole and bury power lines during week of October 8
  • Centerpoint Energy and Consolidated Communication will also schedule work (date TBD) to move and/or protect their lines that will be impacted by construction of the new parking lot